Permit Timeline Calculator
Enter your city, permit type and issue date to estimate when your building permit expires, when the first inspection is due, and the last safe day to apply for renewal.
Predicted expiry
May 24, 2027
180 days from issue, per the city's published rules.
Expires on the 181st day if no inspection scheduled/received; passing inspection extends expiration 180 days
First-inspection deadline
May 24, 2027
180-day inactivity / commencement rule (per the city's published notes)
Renewal window (estimate)
April 24, 2027 – May 24, 2027
Estimated window opening 30 days before expiry. Your AHJ may open renewals earlier or later.
Apply by (smart buffer)
May 17, 2027
Processing time not verified for this city — only the 7-day buffer is applied.
Source: Austin official guidance ↗
Estimate only — verify with your AHJ. Dates are calculated from published city rules for building permits. Codes change, extensions and inspections can move your real deadline, and your permit document always wins. Confirm every date with your local building department before you rely on it.
How it works
Pick your city
Choose one of the 20 verified cities.
Pick the permit type
Building permits are covered; other types are not verified yet.
Enter the issue date
Use the date printed on your issued permit.
Read your dates
Note the predicted expiry, first-inspection deadline, renewal window and apply-by date — then verify them with your AHJ.
Frequently asked questions
How long is a building permit valid?
It depends on the city. Austin, Houston, Chicago and Philadelphia permits are typically valid 180 days from issuance (with inactivity rules), San Diego and San Jose give 12 months, Seattle gives 18 months, and New York City permits can run up to 2 years. Use the calculator above for your city.
When should I apply to renew my permit?
Apply by the expiry date minus your city's processing time minus a 7-day safety buffer. For example, New York City takes about 24 days to process a renewal, so the safe apply-by date is roughly 31 days before expiry.
What is the first-inspection deadline?
Many cities void a permit if no work starts or no inspection happens within 180 days of issuance. Austin permits expire on the 181st day if no inspection is scheduled, and Chicago requires work to begin and a first inspection within 6 months.
Is this calculator's answer official?
No — it is an estimate based on published city rules for building permits in 20 verified US cities. Your permit document and your local building department (AHJ) always win. Confirm every date with them.
Which cities does the timeline calculator cover?
New York, Los Angeles, Chicago, Houston, Phoenix, Philadelphia, San Antonio, San Diego, Dallas, San Jose, Austin, Jacksonville, Fort Worth, Columbus, Charlotte, San Francisco, Indianapolis, Seattle, Denver and Oklahoma City.
More free tools
- Permit Fee & Cost-of-Delay Calculator →
- Shed Permit Checker →
- APN & Parcel Number Lookup →
- License Lookup →
- Noise Ordinance Lookup →
Tired of tracking these dates by hand? Permit Warden watches every permit deadline for you →